In this project we replaced a number of double-glazed glass roof panels at the All England Tennis Club in Wimbledon, London SW19.
Project Detail
- Duration: 7 Days
- Location: Wimbledon, London SW19
Project Scope
- Scaffolding
- Template Existing Glass
- Procure Replacement Panels
- Fit and Seal Replacement Panels
- Remove Scaffolding
Remarks
This was a glass roof over a staircase in the All England Tennis Club Millennium building. The roof was 5 stories high and required specialist scaffolding. The glass panels were an unusual shape and tint which we had to carefully match. The replacement panels were very heavy and took 3-men to install. We also had to comply with strict health and safety requirements.