In this project we supplied and fitted glass balustrades to a balcony at children’s nursery.

Project Detail

  • Duration: 14 Days
  • Location: Raynes Park, London SW20

Project Scope

  • Site survey to work out how many posts we needed.
  • Procurement of posts and fittings.
  • Installation of posts and fittings.
  • Second site survey to ascertain glass dimensions.
  • Procurement of safety glass. (Pilkington)
  • Installation of safety glass.

Remarks

This was a children’s nursery in Wimbledon, London SW19. We began the project by fitting the posts and once this had been completed we were then in a position to get accurate glass dimensions. The overall project took 2 weeks to complete. However, the majority of this time was consumed by delivery lead times.